PWD: Activities of the Roads Division for the Week of November 25, 2024

Date:

Despite the temporary closure of the asphalt plant resulting in reduced road-paving activities, the Public Works Department (PWD) has successfully redirected its crew to other essential tasks. During the week of November 25, 2024, the team cut bushes and cleared drains at various locations on the island while other team members continued to construct drains at New Horizons in Saddlers.

In Basseterre, some team members were dispatched to Carnival Village to grade specific areas with milled material in preparation for the upcoming festivities. Meanwhile, other staff engaged in routine maintenance activities at the Public Works Department.

We will provide additional details on the PWD’s activities as they become available.

Related articles

PWD’s Field Locations for February 11, 2026

Basseterre, St. Kitts (Public Infrastructure NEWS) – On Wednesday, February 11, 2026, the Roads and Drains Division of the...

PWD’s Field Locations for February 10, 2026

Basseterre, St. Kitts (Public Infrastructure NEWS) – While inclement weather conditions have halted some field activities of the asphalt...

PWD’s Field Locations for February 9, 2026

Basseterre, St. Kitts (Public Infrastructure NEWS) – Due to inclement weather conditions, asphalt team operations are temporarily suspended. Concrete...

Last Chance to Submit Proposals; These RFPs Are About to Expire

These RFPs are about to expire; take another look at them before they do: Request for Quotations for Landscaping...
Call Now Button