Construction of the Basseterre Desalination Plant Progresses as the Fusing of Intake Lines Begins

Date:

Basseterre, St. Kitts (MoPIEUDT NEWS) – On Monday, April 7, 2025, MoPIEUDT News returned to the Basseterre Desalination Plant to check in with the Site Supervisor Ben Moise concerning the progress on the pipeline.

Ben worked alongside a handful of his team, surrounded by an array of heavy metal pipes near an operating fusion machine. He explained the crew’s activity.

Site Supervisor Ben Moise

Basseterre Desalination Plant Site Supervisor Ben Moise Comments on Progress at the Site

On Wednesday, April 9, Assistant Water Engineer at the St. Kitts Water Services Department (WSD), Chantal Hanley, spoke briefly about the connectivity between the desalination plant and the storage tank at Morne Peak during her appearance on the WSD’s bi-monthly radio show, The Water Line.

“Currently, we are making good progress. [We] have reached quite far, almost to the top by the reservoir. Right now, [we] are at Bird Rock putting in pipeline.”

– WSD Assistant Water Engineer Chantal Hanley

The construction of the desalination plant is scheduled for July 2025.

Latest Articles

Related articles

Office Closure Announcements for Wednesday, April 23, 2025

The Ministry of Public Infrastructure, Energy, Utilities, and Domestic Transport informs the public that the St. Kitts Water...

See the Water Service Supply Schedule for April 2025

The St. Kitts Water Services Department advises its customers that all information in this table is subject to...

WSD Requests Public Feedback on Water Conservation Campaigns

Basseterre, St. Kitts (MoPIEUDT NEWS) - After implementing three unique campaigns to highlight the importance of water conservation,...

A Recap of the “Save It; Don’t Waste It” Water Conservation Tips

Basseterre, St. Kitts (MoPIEUDT NEWS) - The St. Kitts Water Services Department (WSD) issued a series of water...
Call Now Button