Roads Division Continues Work at Fort Tyson Rise

Date:

Basseterre, St. Kitts (MoPIEUDT NEWS) – Following the demolition and regrading of the roadway at Fort Tyson Rise on February 21 and 22, the concrete and asphalt crews of the Roads Division of the Public Works Department (PWD) continue to improve the roadway in the area.

“The PWD intends make Fort Tyson Rise more comfortable for vehicular use and make some changes to the drainage in the area.”

PWD’s Roads Division Head, Zekey Hazel

This week, the concrete crew is expected to excavate the area as it prepares to lay 8″ pipes and cast concrete drains. Working in concert with the concrete crew, the asphalt crew is also expected to prepare the base for paving, with test paving slated for Wednesday, February 26, 2025.

These activities are part of the ongoing efforts of the Public Works Department to improve public infrastructure on the island.

For the latest news from the PWD and other Departments in the Ministry of Public Infrastructure, Energy, Utilities and Domestic Transport, visit mopieudt.gov.kn and follow us on Facebook.

Latest Articles

Related articles

PWD Roads and Drains Division Activity for Tuesday, July 1, 2025

Basseterre, St. Kitts (MoPIEUDT NEWS) - The Roads and Drains Division of the Public Works Department (PWD) will...

Roads and Drains Division Activities for Monday, June 30, 2025

Basseterre, St. Kitts (MoPIEUDT NEWS) - Today will be another busy day for the team of the Roads...

See the Asphalt Crew’s Activity for June 26 – 27, 2025

Basseterre, St. Kitts (MoPIEUDT NEWS) - On Thursday, June 26, 2025, residents of Bird Rock Commercial Development and...

PWD Road Tracker: June 23, 2025

Basseterre, St. Kitts (MoPIEUDT NEWS) - On Monday, June 23, 2025, the Roads Division of the Public Works...
Call Now Button