PWD: Work on the Retaining Wall at Pump Bay, Sandy Point Continues

Date:

PWD: August Timeline for Constructing a Retaining Wall at Pump Bay, Sandy Point

About the Roadwork Schedule

The schedule publishes the whereabouts of the roads team, the projects in which they engage, the duration of those projects and the nature of the work involved.

Activities

In July 2024, the roads team deployed to Pump Bay, Sandy Point, to build a retaining wall. The project involves multiple activities and most of them have already been completed.

As the project advances to its final stages, the Public Works Department informs the general public that its team will continue its work throughout the week.  According to a work schedule shared by the Roads Team in July, team members are expected to continue laying blocks on August 7, and to engage in backfilling and cleanup activities on August 8 – 9.

The general public is asked to exercise caution when travelling through this area as work continues.

Date & Time

August 7, 2024 (9:00 am) – August 9, 2024 (3:00 pm)

Location

Pump Bay, Sandy Point

Latest Articles

Related articles

PWD’s Activities for August 25 – 26 2025

Basseterre, St. Kitts (MoPIEUDT NEWS) - As residents set out on their morning commutes on Monday, August 25,...

PWD’s Activities for August 21 – 22, 2025

Basseterre, St. Kitts (MoPIEUDT NEWS) – On Thursday, August 21, and Friday, August 22, 2025, the Roads and Drains...

PWD’s Activities for August 18, 2025

Basseterre, St. Kitts (MoPIEUDT NEWS) – The Roads Division of the Public Works Department (PWD) will perform the following...

Public Works Department to Initiate Phased Roadwork at Boyds Project

Basseterre, St. Kitts (MoPIEUDT News) - As the Public Works Department's Roads and Drains Division continues to maintain...
Call Now Button