Schedule PWD: Timeline for Constructing a Retaining Wall at Pump Bay, Sandy Point By: James Morris Date: July 23, 2024 Share post: FacebookTwitterPinterestWhatsApp Activity – July 25 & 26 – Casting of concrete flooring. July 29 – August 7 – Laying of blocks. August 8 & 9 – Backfilling and cleanup. Time & Location – July 15, 2024 (9:00 am) – August 9, 2024 (3:00 pm) Pump Bay, Sandy Point Previous articleProperty Condition Survey for East and West Shadwell to Begin June 29, 2024Next articlePWD: Timeline for Demolishing and Casting Concrete Drains in Lower Monkey Hill Latest Articles See the WSD’s Activity for June 6, 2025 James Morris - June 6, 2025 Hon. Konris Maynard Shares First Progress Update for 2025 Events Water Services Department Shares Progress and Plans at Minister’s Public Session St. Kitts Water Services Department Related articles Schedule PWD: Timeline for Clearing Debris and Bush at the South East Peninsula Activity -The team will be clearing the road of debris and overhanging bushes. Drivers are asked to exercise... Public Works Department Daily Tracker for PWD’s Asphalt Crew Nature of Work:The asphalt crew will be cleaning storm drains.When & Where:July 23, 2024 (9:00 am) - July... Schedule PWD: Timeline for Demolishing and Casting Concrete Drains in Lower Monkey Hill Activity -The crew completed the right side of the drain prior. They will focus on the left side.Time...